Timeline

Significant milestones achieved to date are demonstrated below.

2015
2015

Project Commenced

Investment generally results in acquiring an asset, also called an investment. If the asset is available at a price worth

2016
BusinessCase
2016

Business Case

We commenced the business case and presented to State in 2016

2016
Statkeholder
2016

Engagement

Engaged with Traditional Owners, local government, and communities (2016 to present)

2018
APPROVED@1080x
2018

Approval

Business Case Approved

2019
status
2019

Major Project Status

Received Major Project Status
by WA Premier in 2019

2019
BusinessCase
2019

Mine Minister approval for granting of Crown Lease for a term of 21 years with two (2) 21-year extensions – 63 years in total

2021
Q2.2
2021

Q2 – 2021

Execution of crown lease with
the Department of Lands  

2022
Q3.1
2022

Q3 – 2021

Completion of Environmental approval

2022
Statkeholder
2022

Q1 – 2022

Negotiation of Indigenous land use agreement with the traditional Owners, the Dambimangari people. 

2022
Q3.2
2022

Q3 – 2021 to Q2 – 2022

Front end engineering and design (FEED) 

2022
Q2
2022

Q2 – 2022

+ 8 months construction

Final Investment Decision – Aerodrome 

2022
Q3.2_1
2022

Q3 – 2022

+ 12 months construction

Final Investment Decision – Wharf