Timeline
Significant milestones achieved to date are demonstrated below.
Project Commenced
Investment generally results in acquiring an asset, also called an investment. If the asset is available at a price worth
Business Case
We commenced the business case and presented to State in 2016
Engagement
Engaged with Traditional Owners, local government, and communities (2016 to present)
Approval
Business Case Approved
Major Project Status
Received Major Project Status
by WA Premier in 2019
Mine Minister approval for granting of Crown Lease for a term of 21 years with two (2) 21-year extensions – 63 years in total
Q2 – 2021
Execution of crown lease with
the Department of Lands
Q3 – 2021
Completion of Environmental approval
Q1 – 2022
Negotiation of Indigenous land use agreement with the traditional Owners, the Dambimangari people.
Q3 – 2021 to Q2 – 2022
Front end engineering and design (FEED)
Q2 – 2022
+ 8 months construction
Final Investment Decision – Aerodrome
Q3 – 2022
+ 12 months construction
Final Investment Decision – Wharf